Dylan Patel, founder and CEO of SemiAnalysis, told Molly O'Shea on Sourcery that his firm has pushed multiple gigawatts of planned data-center capacity out of 2027 and into 2028, because the permits to build it are not available.
The usual explanation for slow AI construction is a shortage of money, labor or equipment. Dylan says none of those is the bottleneck, and that the opposition behind the permit fights comes from dislike of AI rather than from people living next to the buildings.
"I think people dislike AI more than they dislike data centers, but data centers are an easy way to point at it." — Dylan Patel
Dylan's firm tracks every data center in the world and sells that research to the hyperscalers, chipmakers and AI labs it regularly criticizes. He has also just raised a $500 million fund and bought a research shop that is bearish on AI.
The full interview is covered here so you can skip it. 51 minutes of audio, 8 minutes of reading.
Here are the 8 insights that matter.
Key Takeaways
Permits, not capital or labor, have pushed multiple gigawatts of data centers from 2027 to 2028
49% of people in counties with a 100-megawatt data center did not know it was there
Products now beat models: Dylan rates Meta's Muse and the Instinct app above OpenAI's Dots
45% of SemiAnalysis's $15 million AI budget now goes to persistent agents, mostly through Perplexity
Anthropic's discount for customers that put 70% of their AI spend with it is "very sticky"
SemiAnalysis is now research, a bearish research shop and a $500 million infrastructure fund
The firm never takes money for an opinion, and criticizes its own biggest customers
1. Permits, Not Money, Delay
Dylan opened on the scale of what SemiAnalysis watches. The firm builds its forecasts from a site-by-site count of the world's data centers.
Dylan Patel says SemiAnalysis knows more about data centers than anyone
"We track every data center in the world. And we, as a firm, know more about data centers than anyone else." — Dylan Patel
That count is what moved the firm's timeline. The delay, he said, comes from water, wastewater, storm-water and air permits that key jurisdictions are not granting.
Dylan Patel says permits alone pushed gigawatts of capacity back a year
"We pushed back multiple gigawatts out of 2027 into 2028... not because they can't build it, not because the labor is not there, not because of some shortage of equipment, but because permits are just not available." — Dylan Patel
He called Texas a bellwether. The state's political messaging favors building, but union-labor mandates and control over permits remain wildcards there.